PROJECT OVERVIEW:

  • Supply and Installation of Permanent Precast Noise WallsThe permanent works consisted of post installation and precast installation on 15 different noise walls throughout the project.  With over 1800 precast panels supplied to the project from 3 different precast suppliers.
  • Design, Supply and Installation of Temporary Noise WallsThe temporary noise wall included an innovative design of a steel noise wall on top of precast barriers, which allowed for no permanent structures or damage to the existing road while construction was carried out.
  • Anti-carbonation Coating of Concrete Structures – Over 40 different concrete structures including Bridges, Retaining Wall, Noise Walls and Barriers were  painted for the project totaling to over 150,694 sq ft of surfaces coated.

YEAR:

2016-2017

LOCATION:

Melbourne, Victoria, Australia